Here’s a brief update regarding activity around Blossom Street. We hope you find this update helpful but please do not hesitate to contact us if you have any questions.

Blossom Street: Extended working hours 15 April 2021

Unfortunately, we have had a problem with concrete works on site this afternoon following the batching plant which we source our concrete from being broken down for a number of hours. As such, we are required to work beyond 6pm this evening in order to complete the works currently in progress. Working with the concrete delivery times which we have been given, it is our hope that all works will be finished by 7pm.

We will endeavour to complete the above works in advance of the times given above if possible. Thank you for your cooperation and we apologise for any inconvenience caused. Please do not hesitate to get in touch if you have any queries.

E: info@blossomstreet-e1.com T: 0800 298 7040

Kind regards,

The Blossom Street Project Team